![]()
By: TOM PFINGSTEN - Staff Writer
FALLBROOK ---- The
With the approval of its major operating permit on Dec. 22, Gregory Canyon
Ltd., the group that has struggled for more than 10 years to build the dump off
Highway 76, three miles east of Interstate 15, gained momentum that could
translate into an early 2006 opening.
"It
has been a long process, and the end is in sight," said Nancy Chase, a
Gregory
Canyon Ltd.'s plans focus on 320 acres of a 1,700-acre site. If the remaining
permits needed for operation are approved before next summer, as expected, said
Chase, the way will be cleared to build a landfill that would accommodate 1
million tons of solid waste each year for 30 years.
Opponents of the project range from local politicians to a
San Luis Rey Rivershed watchdog group to the Pala band of Luiseno Indians.
Lenore Volturno, Pala's environmental director, has vehemently opposed the
project, and traveled to
Even though that council ultimately approved the landfill's
most important permit, Volturno said Thursday: "We're very hopeful that
there will be an agency that will not supply a permit to
Among the complaints that Volturno has voiced are that the
landfill will pollute the tribe's major source of water, the San Luis Rey
River, and that its footprint encroaches on sacred land situated atop a hill
nearby
But the dump is not a sure thing yet.
Bill Hutton, the attorney who handles
Water quality at issue
Perhaps the most consistent accusation leveled against the
landfill by its opponents is that it will negatively affect the quality of
water, both underground and in the nearby San Luis Rey River.
To prevent that from happening ---- and to earn the approval
of a local water board ---- Hutton said that
Between that and a series of monitoring wells that will
detect possible leaks into the groundwater, said Hutton, Gregory Canyon Ltd.
should have no problem securing a water-quality permit.
"It vastly exceeds both the federal and state
standards, and it's something we did to provide an enhanced level of
protection," Hutton said of the lining system. "The likelihood of
pollution from the landfill impacting the uses of groundwater are, in my
opinion, nonexistent with all of the systems we have in place. It's an
exceptionally secure site."
Hutton said that Gregory Canyon Ltd. has several meetings
scheduled with the Regional Water Quality Control Board, after which a formal
permit application will be filed. If the water board approves, the permit will
most likely be issued within 140 days, or some time this summer.
Air is another issue
The quality of air is another point of contention that has
held up landfill development. Pollutants from trash trucks, fumes from the
waste and site dust are three key issues that concern officials with the Air
Pollution Control District.
The application for a permit authorizing and enforcing
air-quality standards for the proposed dump is in the research phase, said
Hutton, adding that preliminary results from that study indicate the landfill
will be able to meet the established standards.
"It addresses everything ---- dust, auto pollutants
like nitrogen oxide, and air toxics, which would largely be a product of
landfill gas," he said. "What we're really seeing is that the thing
we have to control most is just good old dust."
Gregory Canyon Ltd. is in the process of identifying
dust-prevention measures. The completed application will probably be submitted
to the county this spring, said Hutton.
Dredging must be done
If approved, the landfill will be at the base of a set of
hills south of Highway 76, with the San Luis Rey River running between the dump
site and the highway. In order to allow customers to access the facility, a
bridge must be built across the river, a process which requires approval by the
U.S. Army Corps of Engineers.
Even though the actual area that will be dredged to place
bridge pilings amounts to only a very small area, the corps of engineers must
consult with the U.S. Fish and Wildlife Service to ensure that no endangered
species are threatened. Hutton said that Gregory Canyon Ltd. will submit its
application to the corps in one to two months.
Approval for the bridge could be given as soon as this
summer, he said, adding that it is in discussion with the U.S. Fish and
Wildlife Service and that the issue of environmental protection has arisen
repeatedly, said Hutton.
"I understand that the river right now is pretty
degraded," he said. "So we're going to be restoring the riverbed.
About 72 or 73 percent of the
The approximate 1,230 preserve would be furnished with an
outside curator that would work with the dump's operator to ensure that
"the landfill and the habitat coexist with each other," said Hutton.
Miscellaneous permits
Once the last three major permits have been secured, Gregory
Canyon Ltd. will need several other smaller permits for the construction of an
access road, a maintenance building, a water tank and a flare station where
methane gas will be burned off.
"Those are ones that will generally follow, at the time
that you begin actual construction," Hutton said. "We will, on an
ongoing basis, start working on those, but that's a lot of detailed engineering
work."
The permits for grading and other procedural operations
aren't expected to hold up the project's estimated 2006 opening date.
While opponents such as Volturno with the Pala Indian
Reservation will continue to battle the Gregory Canyon project, the landfill's
proponents feel confident as they near the end of a decade of legal battles.
Hutton cites the fact that Gregory Canyon Ltd. has been able
to obtain quotes on a $100 million environmental insurance policy as evidence
that the site is more secure than its detractors say it is.
"No insurance company is going to give us a policy of
that size if there's any risk," he said.
When it opens, Gregory Canyon officials said the landfill
will be open from 7 a.m. to 6 p.m. during the week and from 8 a.m. to 5 p.m. on
Saturday. It will be closed on Sundays. The landfill will not accept green
waste, said Hutton, but may accept some on a limited basis to use as an
alternative cover for the trash, which is usually buried under dirt every
night.
"There will be a drop-off recycling facility, probably
outside the landfill gate," Hutton continued. "We're also going to
accept waste tires, and shred those either onsite or offsite and try to find a
reuse for them."
Contact staff writer Tom Pfingsten at (760) 731-5799 or tpfingsten@nctimes.com